The FMP Blog

How Tilt-Up Walls Are Constructed

  • August 25, 2025

Tilt-up construction has become a popular solution for commercial building projects of all sizes, from warehouses and distribution centers to office parks and retail complexes. 

Known for its speed, efficiency, and cost-effectiveness, the tilt-up method involves casting concrete wall panels horizontally on-site, then lifting them into position to form the building’s exterior shell.

Unlike traditional construction methods that rely heavily on masonry or prefabricated panels, tilt-up combines the benefits of in-place casting with the speed of panelized installation. 

The result is a durable, customizable, and architecturally flexible structure built to last.

This article walks you through the tilt-up construction process, from the initial site preparation to the final structural integration.

Table of Contents

1. Site Preparation
2. Foundation and Floor Slab Construction
3. Panel Design and Layout
4. Formwork Assembly
5. Reinforcement and Hardware Installation
6. Concrete Placement
7. Panel Lifting and Erection
8. Structural Integration and Roof Ties
9. Finishing and Integration


1. Site Preparation

The first step in any tilt-up construction project is preparing the site

Clearing and Grading

This begins with clearing the land of vegetation, debris, old structures, and any other obstructions. 

Once the site is cleared, it must be graded to ensure proper drainage and create a level base for the foundation and slab. 

Proper grading helps prevent future water issues and ensures that both the floor slab and lifting operations are safe and stable.

Compaction and Soil Testing

After grading, the soil is compacted to meet engineering specifications. Soil testing assesses the soil’s load-bearing capacity and moisture content. 

These results guide decisions about slab thickness, reinforcement, and soil amendments or stabilization. 

Compacted, well-tested soil is critical to preventing future settlement or structural failures.

Utility Coordination

Before any concrete is poured or panels are lifted, it’s essential to coordinate with local utility providers. 

Underground water, gas, electric, and telecommunication lines must be located, flagged, and (if necessary) relocated. 

This step prevents delays and ensures the safety of workers and equipment during construction, especially during panel lifting operations when space and movement are restricted.

2. Foundation and Floor Slab Construction

Once the site is prepared, the construction of footings begins.

Footings and Perimeter Foundation

Footings are excavated to the depth specified by the structural engineer, typically below the frost line and per the soil’s bearing capacity. 

Reinforcing steel is installed within the trenches before concrete is poured. Reinforced concrete is significantly stronger, and the footings will play a crucial role in supporting the entire building. 

These footings also provide critical support for the tilt-up panels and serve as the base for anchoring them after they are erected. 

Learn More: Construction Footings: A Complete Introduction

Slab-on-Grade Construction

The next major component is the slab-on-grade, which serves a dual purpose: it is both the building’s finished floor and the casting surface for the concrete panels. 

Because it must support heavy construction equipment and act as a flatbed for forming panels, the slab is built to exacting standards. 

Vapor barriers, reinforcement, and perimeter insulation (where required) are installed before the concrete slab is poured.

Slab Quality Considerations

Flatness and levelness are critical in tilt-up construction. 

According to the TCA (Tilt-Up Concrete Association), the slab must meet high FF (floor flatness) and FL (floor levelness) numbers — typically FF 50 or higher — to ensure that the panels form correctly and can be lifted without damage.

The slab must also achieve a minimum compressive strength (usually around 3,000–4,000 psi) before it can be used as a casting bed. 

This may take several days, depending on the concrete mix and environmental conditions.

Curing

Curing is essential to help the slab achieve its designed strength and durability. 

Methods such as moisture-retaining blankets, continuous water misting, or curing compounds are applied to prevent rapid moisture loss. 

Inadequate curing can result in surface cracking or strength deficiencies, compromising panel casting and future floor performance.

Keep Reading: How Our Concrete Curing Process Maximizes Compressive Strength


3. Panel Design and Layout

Now it’s time to design the tilt-up building to meet the project’s needs while maintaining proper concrete construction standards. 

Engineering Considerations

Before any physical layout begins, each tilt-up panel is designed and engineered to meet the building’s structural demands. 

This includes calculating vertical and lateral loads, factoring in wind, seismic forces, and the weight of the panels themselves. 

General contractors enlist the help of engineers to determine the thickness of the tilt-up concrete panels, the amount and type of reinforcement required, and the necessary lifting inserts.

Architectural and Structural Input

tilt-up wall

In parallel with structural design, architectural teams finalize the layout and appearance of each panel. 

This includes much more than just the building’s square feet. It involves the placement of:

  • Doors
  • Windows
  • Recesses
  • Reveals
  • Embedded finishes 

The tilt-up method allows for great design flexibility; panels can be textured, colored, and even curved.

On-Slab Layout

Once the slab has cured and been inspected, the layout crew uses full-scale drawings to mark the exact dimensions of each panel directly on the floor slab. 

Using chalk lines, lasers, or total stations, they outline:

  • Exterior and interior panel edges
  • Openings and block-outs (e.g., windows, doors, mechanical penetrations)
  • Locations of embedded items like plates, conduits, and lifting inserts

The chalk outlines serve as the template for constructing the panel forms in the next step.

When considering tilt-up methods, it’s useful to understand the differences between concrete and masonry for structural and design decisions.


4. Formwork Assembly

The parts of formwork assembly include:

Constructing Panel Molds

With the panel outlines chalked onto the slab, construction of the panel molds, or formwork, begins. 

These molds are typically built from high-quality dimensional lumber, plywood, or reusable aluminum forms. 

The edges are cut and fastened to match the exact dimensions of each panel, including openings for windows, doors, and utility penetrations. 

Applying Bond Breakers

Before any concrete is poured, a bond breaker is applied to the slab’s surface within the formwork area. 

This chemical agent prevents the cast panel from adhering to the slab during curing. The bond breaker must be evenly sprayed or rolled on and allowed to dry thoroughly, ensuring clean panel separation at lift time. 

Setting Block-Outs and Embeds

After the perimeter forms are secured, crews place all block-outs, which are temporary inserts used to create openings for windows, doors, and utility penetrations. 

These are often made from foam or wood and are custom-cut to match architectural drawings. 

In addition, a variety of embedded items are installed:

  • Weld plates and anchor inserts
  • Conduits and electrical boxes
  • Lifting inserts and bracing hardware

These elements must be precisely positioned to align with structural and mechanical plans. Engineers typically verify their location before concrete placement.

If form liners will be used to add exterior texture, this is the time to do so. 

5. Reinforcement and Hardware Installation

Once the formwork is in place and cleaned, the structural reinforcements are installed within each panel mold.

Rebar and Mesh Placement

The layout of rebar follows the engineering drawings and is critical for ensuring the panel’s strength during lifting, placement, and in-service loading. 

Depending on the panel’s size, shape, and structural requirements, this may include:

  • Horizontal and vertical bars (typically #4 or #5)
  • Overlapping splices where specified
  • Shear or diagonal reinforcement if required

In some designs, welded wire mesh is used as supplemental or primary reinforcement, especially in thinner or less complex panels. 

Lifting and Bracing Inserts

Strategically located lifting inserts, typically made of steel, are embedded in the panel to enable the crane to safely pick and rotate the panel into a vertical position. 

These inserts must be:

  • Properly aligned according to the lift plan
  • Secured firmly to rebar to resist shifting during the pour
  • Inspected before concrete placement

Additionally, bracing inserts or anchors are embedded to accept temporary braces that stabilize the panel after it is lifted, but before the roof or adjacent panels are connected.

Conduit and Electrical Embeds

Panels that include electrical systems, plumbing chases, or low-voltage wiring may require embedded conduit, junction boxes, or sleeves. 

These elements must be installed with precision so they align with the building’s future mechanical and electrical layout.

Final Inspection

Forms, hardware, and reinforcement are reviewed by project engineers and inspectors for code compliance.


6. Concrete Placement

The concrete pour begins once reinforcement and hardware have been inspected and approved.

Pouring Concrete

Concrete is typically delivered by ready-mix trucks and placed into the horizontal panel forms using pump trucks or direct chute discharge. 

Crews carefully distribute the concrete across the panel, ensuring complete coverage without disturbing embedded items or reinforcement.

Placement is done methodically to:

  • Avoid segregation of aggregate
  • Prevent trapping air beneath or around block-outs and inserts
  • Ensure consistent panel thickness throughout

Crews often pour panels in a sequence that matches the crane lifting order to improve workflow and minimize curing delays.

Finishing the Panel Face

As the concrete is poured, it must be vibrated and consolidated to eliminate air pockets (voids) and ensure it surrounds rebar, embeds, and complex block-outs. 

This is typically done using internal mechanical vibrators, which are inserted into the wet concrete in a grid-like pattern.

Curing

Once finishing is complete, the panels must be moist-cured to allow the concrete to gain strength and durability. 

Curing methods can include:

  • Wet burlap or curing blankets
  • Continuous water misting
  • Spray-on curing compounds (if compatible with bond breaker and finishing materials)

Most tilt-up panels must achieve a minimum compressive strength of 2,500–3,500 psi before they can be safely lifted, as specified in the project’s engineered lift plan. 

This typically takes 3-7 days, depending on mix design, temperature, and humidity.


7. Panel Lifting and Erection

Once the panels have cured to the required strength, the site is prepared for lifting.

Crane Setup and Rigging

A mobile crane, sized appropriately for the panel weight and reach, is brought in and set up on firm, level ground. Before lifting starts, the lifting plan is reviewed and finalized according to details like:

  • Rigging configuration (cables, shackles, spreader bars)
  • Lift points and angles
  • Panel sequence and rotation path
  • Safety zones and personnel roles

Crane setup and operation must comply with OSHA and project-specific safety protocols.

Lifting Each Panel

With all safety checks complete, the crane slowly begins the lift. The panel is raised vertically off the casting slab and gently rotated into its upright position. 

Often dramatic and highly choreographed, this process requires extreme care to avoid twisting, cracking, or collisions. 

Once vertical, the panel is moved to its final position, with the interior walls followed by the exterior walls. Each panel is carefully aligned over anchor bolts or dowels and gently lowered into place.

Temporary Bracing

Once placed, panels are secured with adjustable steel braces until the roof and floor systems lock them into a permanent position.

Safety Measures

Panel erection is one of the most hazard-sensitive stages in tilt-up construction. Strict adherence to safety protocols is essential.

A single misstep during lifting can compromise structural integrity or result in serious injury. Planning, coordination, and oversight are non-negotiable.


8. Structural Integration and Roof Ties

With panels standing and temporarily braced, the next phase begins.

Connecting the Roof Structure

tilt-up wall construction

Installing the roof system involves erecting steel columns and beams, setting bar joists, girders, or trusses, and installing metal decking or concrete planks.

The roof system ties the walls together, distributing lateral loads like wind and seismic forces throughout the structure. 

Coordination with the steel erection crew is essential at this stage to ensure sequencing aligns with panel placement.

Creating Diaphragm Action

The roof acts as a horizontal diaphragm, meaning it helps resist and redistribute horizontal forces across the building. 

Once connected to the wall panels, the roof system enables the structure to behave as a single, cohesive unit.

Connecting the roof system to the wall panels with welded or bolted hardware completes the lateral load path.

Load Transfer and Panel Alignment

After the roof structure is partially or fully installed, crews return to verify and adjust the alignment of each panel by:

  • Checking verticality and plumbing using laser or total station tools
  • Aligning panel tops with the roof steel
  • Welding or bolting panels to adjacent panels and roof members

Structural ties — like weld plates or tie rods — are installed to secure the panels at designated connection points.

Bracing Removal

Once the roof and necessary connections are in place and inspected, temporary bracing is systematically removed under the supervision of engineers to ensure safety and sequencing.


9. Finishing and Integration

The final step in completing tilt-up projects involves a few finishing touches.

Panel Connections

After all panels are in place and structurally tied together, the vertical and horizontal joints between panels are sealed to protect the building envelope.

Included in this process are:

  • Cleaning joint surfaces thoroughly to ensure adhesion
  • Installing backer rods where required
  • Applying high-performance elastomeric sealants or caulk

Proper joint sealing prevents water intrusion, air leakage, and thermal bridging. It also improves the building’s acoustics, energy efficiency, and fire resistance.

Interior and Exterior Finishes

Depending on the design intent, the exposed face of each panel may receive additional architectural finishes or coatings.

In many cases, the desired finish is already achieved during casting, particularly when form liners or integral colorants are used. Still, touch-ups may be required to correct blemishes or complete transitions.

Utility Integration

As exterior work wraps up, attention shifts inward. Utility crews begin connecting the building’s embedded systems to active services.

Any embedded conduits installed during panel casting are tied into the building’s central systems, reducing the need for surface-mounted utilities and contributing to a clean, professional interior finish.


Recap

When executed correctly, tilt-up concrete delivers faster timelines, reduced material waste, and lower labor costs compared to precast concrete construction. This makes it a wise choice for both commercial developers and property owners.

With the right team in place, tilt-up is more than just an efficient building method; it’s a powerful tool for delivering high-quality commercial spaces that stand the test of time.

If you’re considering tilt-up construction for your next project, contact FMP Construction to discuss the possibilities.

Latest Posts

© 2025 FMP Construction. All rights reserved.